State:                                      KENTUCKY

 

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Agency:                                   KENTUCKY TRANSPORTATION CABINET - DISTRICT 8                          

                                                                                                                                                                              

Project and/or Route Name: INTERSTATE 66-PULASKI COUNTY – PHASE I

 

Dates:                                     2000 – PRESENT

 

Rural and/or Urban:              RURAL

 

Length:                                   8 Miles

 

Type of Improvement:          4-LANE RURAL INTERSTATE

 

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Firm's Project Manager:       MICHAEL G. BRUCE, P.E., L.S., VICE PRESIDENT, FIRM PRINCIPAL      

Firm's Project Engineer:      THOMAS D. WILLIAMS, P.E., PROJECT DESIGN ENGINEER                    

Firm's Structural Engr.:        DAVID C. DEPP, P.E., CHIEF STRUCTURAL ENGINEER                            

Firm's Project QA/QC Engr.: WILLIAM B. WEST, P.E., DESIGN CONSULTANT & QA/QC

 

Project Description:  

The scope of this project is to provide professional engineering services for the completion of Phase I Design, including preparation of design studies, and environmental services necessary to prepare an environmental document to secure location approval for a section of Interstate 66 from the Cumberland Parkway west of Somerset to KY 80 east of Somerset.

 

The Consultant was responsible for:

 

JDQ will serve as Project Manager for the entire 8 mile Phase I design segment and also is responsible for detailed design of the alignment segments, which includes four interchanges.

 

PROJECT MANAGEMENT:  JDQ will serve as project manager; schedule meetings; write minutes; provide overall design criteria to team members to expedite uniformity of plan development, and be responsible for the Phase I Design as detailed below.

 

PHASE I DESIGN:

 

1.         All necessary field surveys, including check sections, drainage and environmental area identification.

 

2.         Public involvement plan, including newsletters, citizens Advisory Council, public information meetings, slide presentations press releases.

 

3.         Phase I alignments within designated corridor, including horizontal and vertical mainline alignments, cross-road alignments and interchange geometry.

 

The Department was responsible for:

 

1.         Traffic counts and traffic movements.

 

2.         Pavement design catalog.