State: KENTUCKY Agency: KENTUCKY TRANSPORTATION CABINET -
DISTRICT 1 Project and/or Route Name: US HWY. 641 OVER EAST
FORK CLARKS RIVER MARSHALL COUNTY Dates: 1982 -
1984 Rural
and/or Urban: RURAL Length: 400 FEET Type of
Improvement: BRIDGE REPLACEMENT Firm's Project Manager: PAUL L. HENDRICK, P.E., ASSOCIATE FIRM
PRINCIPAL Firm's Project Engineer: WILLIAM H. McKINNEY, P.E., PROJECT DESIGN
ENGINEER Project
Description : This bridge was a replacement for an older steel
truss bridge downstream from the new location. Traffic used the old bridge until the new bridge was completed
and traffic could be rerouted on the new bridge. The structure is made up of four spans of 96, 100', 100', and
96', for a total length of 398'. The
framing consists of six rows of Type 4 Prestressed Concrete I-Beams acting
compositely with a cast-in-place concrete deck. The main piers are founded on concrete friction piles as well
as the abutments. Sheet pile
cofferdams were required at the piers adjacent to the river. Seismic forces played a major part in the design
of the piers because of the bridge being located in a high seismic zone. The design was completed in 1984 and
construction was finished in 1987.
The estimated cost of the bridge is $775,000. The
Consultant was responsible for: The Department was
responsible for: 1. Providing surveys. 1. Geotechnical work. 2. All design and construction plans. 2. Advance Situation Folder. 3. Specifications
and cost estimates. 3. Geotechnical work. |